This Video addresses Interconnection Bottlenecks as an overview of the whole process.
Original Message:
Sent: 09-16-2024 06:29 PM
From: Timothy Mcbride
Subject: Interconnection Bottlenecks
------------------------------
Timothy Mcbride
CEOOwner
Sol-Era R & D
Original Message:
Sent: 09-16-2024 08:47 AM
From: Emily Moog
Subject: Interconnection Bottlenecks
Short answer: This is a legal question better addressed to the entity that owns the equipment that needs upgrading for the project, and/or a lawyer with appropriate specialization.
Slightly less short answer: My understanding is that (in general) the developer is, in essence, paying the utility or other grid entity to defray the costs of the upgrade, and so the equipment is owned by the grid entity. However, I've heard anecdotally that there sometimes are more complicated arrangements for some projects, so I really do recommend that you seek advice from a lawyer with expertise in this area.
------------------------------
Emily Moog
Original Message:
Sent: 09-13-2024 03:02 PM
From: Atilla Akarsu
Subject: Interconnection Bottlenecks
We have been in the DD process of MISO located Project. When new solar projects seek interconnection, significant grid upgrades are often required to accommodate the additional capacity. We have seen that these upgrade costs will be allocated to developers. No reimbursement mechanism on the cost will be spent to upgrade the grid.
Even if all system upgrade and Transmission switchyard costs are covered by the developer, does ownership pass to the Transmission System Provider?
------------------------------
Atilla Akarsu
Business Development and M&A Manager
Sabanci Renewables Inc.
------------------------------